Stage three - update

In addition to the below, the removal of existing lines will now be taking place Sunday, August 20, 2023 from 2.30pm to 10pm.

While every effort will be made to minimise impacts to nearby residents, noise is expected during this time with various plant and equipment on site for the line removal.

As previously shared, stage three will include line marking and installation of median islands. Works will be completed as nightworks to limit traffic disruptions in the area and is commencing on Monday, August 21, 2023. It is expected to take approximately three nights to complete, weather pending. Working hours will be 6pm to 6am and some noise is expected to be associated with the works.

During the works, traffic control will be in place. Motorists and pedestrians are advised to please follow all signage in the area to ensure their safety. All attempts will be made to minimise the impact on residents and road users.

Council apologises for any inconvenience caused and we appreciate your patience during these essential works.

Should you have any questions about this project, please contact site supervisor Jason McKinlay on 0408 791 698 or Benjamin Crowley on 1300 MACKAY (622 529).

Share Stage three - update on Facebook Share Stage three - update on Twitter Share Stage three - update on Linkedin Email Stage three - update link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>