Share Marwood-Sunnyside Road shoulder widening on FacebookShare Marwood-Sunnyside Road shoulder widening on TwitterShare Marwood-Sunnyside Road shoulder widening on LinkedinEmail Marwood-Sunnyside Road shoulder widening link
Council will be completing works on Marwood-Sunnyside Road in Balberra.
Council will be upgrading drainage by replacing existing culverts at three sites and widening the road shoulder on the northern side of Marwood-Sunnyside Road. Please see map in the photos panel to the right.
Works will commence at the McDonalds Road end of Marwood-Sunnyside Road and progress towards the Bruce Highway.
Site crews will be mobilising in the area from Monday, January 10 with works expecting to commence later in the week. It is anticipated the project will be completed in November, weather permitting.
Works will be completed Monday to Friday between the hours of 6am and 6pm, and weekends when required.
There will be driveway interruptions for some residents, these residents will be contacted by the site supervisor prior to works commencing to discuss your access requirements.
The works will be completed under traffic control. Temporary traffic signals will be installed with one-way traffic for the project. We ask motorists to please follow all signage and instructions
There will be some noise and dust disturbances due to various plant and equipment that will be used on site.
Council apologises for any inconveniences caused and we appreciated your patience during these works.
Should you have any questions about the project, please contact our site supervisor Don De Rin Perette on 1300 MACKAY (622 529)
Council will be completing works on Marwood-Sunnyside Road in Balberra.
Council will be upgrading drainage by replacing existing culverts at three sites and widening the road shoulder on the northern side of Marwood-Sunnyside Road. Please see map in the photos panel to the right.
Works will commence at the McDonalds Road end of Marwood-Sunnyside Road and progress towards the Bruce Highway.
Site crews will be mobilising in the area from Monday, January 10 with works expecting to commence later in the week. It is anticipated the project will be completed in November, weather permitting.
Works will be completed Monday to Friday between the hours of 6am and 6pm, and weekends when required.
There will be driveway interruptions for some residents, these residents will be contacted by the site supervisor prior to works commencing to discuss your access requirements.
The works will be completed under traffic control. Temporary traffic signals will be installed with one-way traffic for the project. We ask motorists to please follow all signage and instructions
There will be some noise and dust disturbances due to various plant and equipment that will be used on site.
Council apologises for any inconveniences caused and we appreciated your patience during these works.
Should you have any questions about the project, please contact our site supervisor Don De Rin Perette on 1300 MACKAY (622 529)
Page last updated: 04 Oct 2022, 08:57 AM
Custom
Area: Balberra
Status: Construction to start January, 2022, weather permitting.
Timeline
Construction stage
Marwood-Sunnyside Road shoulder widening is currently at this stage
Construction is expected to start early January 2022, weather permitting.
Construction complete
this is an upcoming stage for Marwood-Sunnyside Road shoulder widening