Project update: This project is completed.
Works on Mirani No. 3 reservoir will eliminate the need to build a new reservoir in the near future saving ratepayers money.
The ground-level reservoir, located on Mirani-Bolden Road, provides water storage for the Mirani township.
The works are set to begin during November and are expected to run until the end of March 2023, weather permitting.
Work will take place Monday to Saturday between 6.30am to 6.30pm. Impacts to residents are expected to be minimal with some possibly experiencing low water pressure at times during works.
Motorists using Mirani-Boldon Road are asked to be cautious as additional trucks will be entering and exiting the site. Traffic signs will be in place.
For more information, contact council's Community Engagement team on 1300 MACKAY (622 529).
Project update: This project is completed.
Works on Mirani No. 3 reservoir will eliminate the need to build a new reservoir in the near future saving ratepayers money.
The ground-level reservoir, located on Mirani-Bolden Road, provides water storage for the Mirani township.
The works are set to begin during November and are expected to run until the end of March 2023, weather permitting.
Work will take place Monday to Saturday between 6.30am to 6.30pm. Impacts to residents are expected to be minimal with some possibly experiencing low water pressure at times during works.
Motorists using Mirani-Boldon Road are asked to be cautious as additional trucks will be entering and exiting the site. Traffic signs will be in place.
For more information, contact council's Community Engagement team on 1300 MACKAY (622 529).
Share Works are complete for the Mirani reservoir upgrade on FacebookShare Works are complete for the Mirani reservoir upgrade on TwitterShare Works are complete for the Mirani reservoir upgrade on LinkedinEmail Works are complete for the Mirani reservoir upgrade link
Council thanks the community for their patience while these essential works were undertaken.
Custom
Area: Mirani
Status: Completed
Published: November 7, 2022 - archived
Lifecycle
Construction begins
Mirani reservoir upgrade has finished this stage
Construction completed
Mirani reservoir upgrade is currently at this stage